MISO-J466
30 MW storage in Huron, MI · In queue since May 2015 · Proposed COD October 2015
30 MW
Capacity
1
Components
Battery
11y 2m
In Queue
IA Executed
IA Phase
Signed Jul 2017
Queue → IA
2y 2m
Total Duration
2y 2m
Schedule
130 months past proposed COD
Study Phase
DPP-2015-AUG East (ITC)
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2015-10-22
MISO-J466 is a proposed 30 MW battery storage project located in Michigan within the Midcontinent Independent System Operator (MISO) region. The project consists of a single 30 MW battery component. Its point of interconnection is the Stein 345 kV Substation.
The project entered the MISO interconnection queue on May 18, 2015, with a proposed commercial operation date of October 1, 2016. The interconnection agreement (IA) for the project has been executed.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MI
County
Huron
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
—
Point of Interconnection
Stein 345 kV Substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- DECO.BROOKFLD1
- POI Substation
- Stein Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J466Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.