MISO-J4306
300 MW generation in Ford · In queue since September 2026 · Proposed COD June 2031
300 MW
Capacity
0
Components
1 month
In Queue
—
IA Status
COD target: 2031
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-06-30
MISO-J4306 is a proposed 300 MW generation project located in Ford County, listed in the interconnection queue of the Midcontinent Independent System Operator (MISO). The project's technology is classified as "Other" in the queue data. The associated transmission owner is Northern States Power Company. The project data does not identify a developer, a state, or a specific point of interconnection; the point of interconnection is recorded only as "Other_".
The project entered the MISO queue on September 8, 2026, and is currently listed with an active status. It has requested Network Resource Interconnection Service (NRIS), and its proposed commercial operation date is June 30, 2031. The available data does not specify the status of an interconnection agreement.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
—
County
Ford
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
NORTHERN STATES POWER COMPANY
Entity
MISO
Service Type
NRIS
Point of Interconnection
Other_
Data Source
Live · MISO
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J4306Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.