MISO-J4083
150 MW storage in Perry, MS · In queue since October 2025 · Proposed COD June 2030
150 MW
Capacity
1
Components
Battery
9 months
In Queue
—
IA Status
COD target: 2030
Total Duration
4y 8m
Study Phase
DPP Cycle Pending South
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-06-30
MISO-J4083 is a proposed 150 MW battery storage project located in Perry County, Mississippi. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of October 7, 2025. Cooperative Energy is listed as the utility.
The project's interconnection service type is Network Resource Interconnection Service (NRIS). As of the latest data, the project has an active status in the MISO queue.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MS
County
Perry
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
COOPERATIVE ENERGY
Entity
MISO
Service Type
NRIS
Point of Interconnection
Purvis Bulk 161 - Hintonville 161 161.0kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J4083Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.