MISO-J4068
232 MW generation in Marshall, IA · In queue since October 2025 · Proposed COD August 2030
232 MW
Capacity
1
Components
Wind
9 months
In Queue
—
IA Status
COD target: 2030
Total Duration
4y 10m
Study Phase
DPP Cycle Pending West
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-08-01
MISO-J4068 is a proposed wind generation project with a total capacity of 232 MW. The project is located in Marshall County, Iowa, and is interconnected within the Midcontinent Independent System Operator (MISO) region. The queue entry date for MISO-J4068 is October 3, 2025.
The project's point of interconnection (POI) is the Lehigh - Marshalltown (Twinkle) 345kV substation. The project is currently in Phase 1 of the study phase and is designated as a Network Resource Interconnection Service (NRIS). The project's status is listed as active within the MISO interconnection queue.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IA
County
Marshall
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
NRIS
Point of Interconnection
Lehigh - Marshalltown (Twinkle) 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J4068Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.