MISO-J3979
200 MW hybrid in Sullivan, IN · In queue since April 2025 · Proposed COD October 2029
200 MW
Capacity
1
Components
Solar
1y 3m
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 6m
Study Phase
DPP Cycle Pending Central
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-10-01
MISO-J3979 is a proposed 200 MW hybrid generation project located in Sullivan County, Indiana. The project, which is in the MISO interconnection queue, entered the queue on April 8, 2025. Duke Energy Indiana, LLC is the utility associated with the project, which is interconnecting at the Petersburg - Sullivan (AEP/PJM) 345.0kV point of interconnection. The project is currently in Phase 1 of its study phase and has an active status.
The project is seeking Network Resource Interconnection Service (NRIS). No proposed commercial operation date or interconnection agreement (IA) status is available. The developer is not specified in the data. The technology is listed as "Other" with the detail specifying "Hybrid".
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IN
County
Sullivan
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
INDIANAPOLIS POWER & LIGHT COMPANY
Entity
MISO
Service Type
NRIS
Point of Interconnection
Petersburg - Sullivan (AEP/PJM) 345.0kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J3979Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.