MISO-J3902
288.5 MW generation in Jefferson, TX · In queue since February 2025 · Proposed COD June 2028
288.5 MW
Capacity
1
Components
Wind
1y 5m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 4m
Study Phase
DPP Cycle Pending South
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
MISO-J3902 is a proposed wind generation project with a total capacity of 288.5 MW. The project is located in Jefferson County, Texas, within the Entergy Texas service area. It is listed in the MISO interconnection queue as of February 6, 2025. The project's interconnection service type is NRIS (Network Resource Interconnection Service), and it is currently in Phase 1 of the study process.
The proposed project is listed as active in the MISO queue. The point of interconnection (POI) is the Stowell substation.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Jefferson
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY TEXAS, INC.
Entity
MISO
Service Type
NRIS
Point of Interconnection
STOWELL
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- TEXAS.HUB
- Hub Confidence
- HIGH
- POI Substation
- Stowell Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J3902Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.