MISO-J3872
350 MW storage in Wayne, MI · In queue since January 2025 · Proposed COD January 2029
350 MW
Capacity
1
Components
Battery
1y 6m
In Queue
—
IA Status
COD target: 2029
Total Duration
4 years
Study Phase
DPP Cycle Pending East (ITC)
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-01-05
MISO-J3872 is a proposed 350 MW battery storage project located in Wayne County, Michigan. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue with an entry date of January 27, 2025. The proposed project is currently in Phase 1 of the interconnection study process and intends to provide Network Resource Interconnection Service (NRIS). The interconnecting utility is ITC.
The development project is listed as "active" in the MISO queue. No proposed commercial operation date or interconnection agreement (IA) status is available. There is no match to an existing Energy Information Administration (EIA) operating plant, and no news coverage is available for this project.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MI
County
Wayne
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC
Entity
MISO
Service Type
NRIS
Point of Interconnection
RIVER ROUGE
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- DECO.RRP11
- POI Substation
- River Rouge Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J3872Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.