MISO-J3865
250 MW generation in Shiawassee, MI · In queue since December 2024 · Proposed COD November 2028
250 MW
Capacity
1
Components
Wind
1y 7m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 11m
Study Phase
DPP Cycle Pending East (ITC)
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-11-01
The proposed MISO-J3865 project is a 250 MW wind generation facility located in Shiawassee County, Michigan. The project was entered into the MISO interconnection queue on December 8, 2024, with a proposed commercial operation date of November 1, 2028. The interconnecting utility is METC.
The project, sponsored by an unknown developer, is currently listed as active in the MISO queue. The point of interconnection is the CORNELL - LAYTON 138.0kV line. There is no record of an interconnection agreement (IA) for this project in the provided data, nor is there any indication of a match to an existing operating plant or recent news coverage.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MI
County
Shiawassee
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
NRIS
Point of Interconnection
CORNELL - LAYTON 138.0kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J3865Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.