MISO-J3864
230 MW generation in Shiawassee, MI · In queue since December 2024 · Proposed COD November 2028
230 MW
Capacity
1
Components
Wind
1y 7m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 11m
Study Phase
DPP Cycle Pending East (ITC)
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-11-01
MISO-J3864 is a proposed wind generation project with a total capacity of 230 MW, located in Shiawassee County, Michigan. The project is in the MISO interconnection queue, having entered the queue on December 9, 2024, under the utility METC. The proposed commercial operation date is November 1, 2028. The point of interconnection is the GOSS - THETFORD 345.0kV line.
The development project consists of 230 MW of wind generation capacity. As of the latest data, the project's interconnection status is active, meaning it is still under consideration within the MISO queue.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MI
County
Shiawassee
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
NRIS
Point of Interconnection
GOSS - THETFORD 345.0kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.