MISO-J3787
247 MW generation in Stutsman, ND · In queue since April 2024 · Proposed COD June 2028
247 MW
Capacity
1
Components
Solar
2y 3m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2028
Total Duration
4y 2m
Study Phase
DPP-2023 West
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-30
MISO-J3787 is a proposed solar generation project with a total capacity of 247 MW. The project is located in Stutsman County, North Dakota, and is being developed within the Midcontinent Independent System Operator (MISO) region. Otter Tail Power Company is the interconnecting utility.
The project entered the MISO interconnection queue on April 16, 2024, with a proposed commercial operation date of June 30, 2028. The point of interconnection (POI) is the Jamestown 345 kV Substation. As of the current data, the project's interconnection agreement (IA) status is not specified.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
ND
County
Stutsman
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
OTTER TAIL POWER COMPANY
Entity
MISO
Service Type
NRIS
Point of Interconnection
Jamestown 345 kV Substation
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- OTP.JAMSPK1
- POI Substation
- Jamestown Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J3787Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.