MISO-J3731
160 MW generation in Knox, IN · In queue since April 2024 · Proposed COD January 2027
160 MW
Capacity
1
Components
Solar
2y 3m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2027
Total Duration
2y 9m
Study Phase
DPP-2023 Central
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-01-31
The proposed MISO-J3731 project is a 160 MW solar generation project located in Knox County, Indiana. The project is interconnected within the Midcontinent Independent System Operator (MISO) queue, having entered the queue on April 17, 2024. Duke Energy Indiana is the utility associated with the interconnection.
The proposed commercial operation date for the MISO-J3731 project is January 31, 2027. The point of interconnection is the Edwardsport - Vincennes 138.0kV line. As of the current data, the project's interconnection agreement (IA) status is not specified.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IN
County
Knox
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
DUKE ENERGY INDIANA
Entity
MISO
Service Type
NRIS
Point of Interconnection
Edwardsport - Vincennes 138.0kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J3731Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.