MISO-J3586
205.8 MW hybrid in Montgomery, TX · In queue since April 2024 · Proposed COD January 2028
205.8 MW
Capacity
1
Components
Solar
2y 3m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2028
Total Duration
3y 9m
Study Phase
DPP-2023 South
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-01-01
MISO-J3586 is a proposed 250.55 MW hybrid solar and battery project located in Grenada County, Mississippi. The project, which interconnects with Entergy Mississippi, is in the MISO interconnection queue as of April 18, 2024, with a proposed commercial operation date of January 1, 2028. The point of interconnection is at the Indianola 230/115 kV substation - Tillatoba 230.0 kV line.
The development project consists of 250.55 MW of solar capacity, and also includes a battery component. It is currently listed as an active project in the MISO queue. The project has appeared in recent news coverage regarding energy development in the region.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Montgomery
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY TEXAS, INC.
Entity
MISO
Service Type
NRIS
Point of Interconnection
JACINTO - PEACH CREEK 230.0kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J3586Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.