MISO-J3565
100 MW storage in Champaign, IL · In queue since April 2024 · Proposed COD August 2028
100 MW
Capacity
1
Components
Battery
2y 3m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2028
Total Duration
4y 4m
Study Phase
DPP-2023 Central
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-08-01
The proposed MISO-J3565 development project is a 100 MW battery storage project located in Champaign County, Illinois. It is interconnected to the Ameren Transmission Company of Illinois system. The project entered the MISO interconnection queue on April 18, 2024, with a proposed commercial operation date of August 1, 2028.
The project consists of a single 100 MW battery component. As of the current data, the project's interconnection agreement (IA) status is not specified.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IL
County
Champaign
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN TRANSMISSION COMPANY OF ILLINOIS
Entity
MISO
Service Type
NRIS
Point of Interconnection
Rising
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- HIGH
- POI Substation
- Rising Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J3565Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.