MISO-J3515
199.9 MW storage in Sangamon, IL · In queue since April 2024 · Proposed COD May 2026
199.9 MW
Capacity
1
Components
Battery
2y 3m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2026
Total Duration
2y 1m
Schedule
2 months past proposed COD
Study Phase
DPP-2023 Central
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-05-25
MISO-J3515 is a proposed energy storage project located in Sangamon County, Illinois, within the Midcontinent Independent System Operator (MISO) region. The project, with a total capacity of 199.9 MW, consists entirely of battery storage technology. The interconnecting utility is City Water Light & Power.
The project entered the MISO interconnection queue on April 17, 2024, with a proposed commercial operation date of May 25, 2026. As of the current data, the project is listed as active in the queue and no interconnection agreement (IA) status is available. The point of interconnection (POI) is listed as 343505 Interstate.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IL
County
Sangamon
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
CITY WATER LIGHT & POWER
Entity
MISO
Service Type
ERIS
Point of Interconnection
343505 Interstate
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- CWLP.INTERSA81
- POI Substation
- Interstate
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J3515Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.