MISO-J3368
199.9 MW generation in St. Landry Parish, LA · In queue since April 2024 · Proposed COD October 2028
199.9 MW
Capacity
1
Components
Wind
2y 3m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2028
Total Duration
4y 6m
Study Phase
DPP-2023 South
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-30
MISO-J3368 is a proposed wind generation project with a total capacity of 199.9 MW. The project is located in St. Landry Parish, Louisiana, and is being developed within the Midcontinent Independent System Operator (MISO) region. The project entered the MISO interconnection queue on April 18, 2024, with a proposed commercial operation date of October 30, 2028. The designated point of interconnection (POI) is West Fork.
The project is sponsored by CLECO POWER and is currently listed as active in the interconnection queue. There is no interconnection agreement (IA) status available in the provided data, nor is there a match to an existing operating plant in the EIA database. Recent news coverage of the project could not be confirmed based on the provided information.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
LA
County
St. Landry Parish
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
CLECO POWER
Entity
MISO
Service Type
NRIS
Point of Interconnection
Ville Platte - West Fork 230.0kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- HIGH
- POI Substation
- West Fork Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J3368Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.