MISO-J3160
100 MW storage in Fond Du Lac, WI · In queue since September 2022 · Proposed COD June 2027
100 MW
Capacity
1
Components
Battery
3y 10m
In Queue
Cluster Study
IA Phase
COD target: 2027
Total Duration
4y 9m
Study Phase
DPP-2022 East (ATC)
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-30
MISO-J3160 is a proposed 100 MW battery storage project located in Fond Du Lac County, Wisconsin. The project, which consists entirely of battery storage, is in the Midcontinent Independent System Operator (MISO) interconnection queue. It entered the queue on September 14, 2022, with a proposed commercial operation date of June 30, 2027. The interconnection agreement is currently listed as "In Progress (unknown study)".
The project is interconnected to the American Transmission Company (ATC) system at the South Fond du Lac 345 kV point of interconnection. The project is currently listed as active in the MISO queue.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
WI
County
Fond Du Lac
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMERICAN TRANSMISSION COMPANY
Entity
MISO
Service Type
NRIS
Point of Interconnection
South Fond du Lac 345 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- ALTE.SFONDDLG1
- POI Substation
- South Fond du Lac Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J3160Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.