MISO-J2982
35 MW generation in Warren, IL · In queue since September 2022 · Proposed COD September 2023
35 MW
Capacity
1
Components
Solar
3y 10m
In Queue
Cluster Study
IA Phase
COD target: 2023
Total Duration
1 year
Schedule
34 months past proposed COD
Study Phase
DPP-2022 Central
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-09-30
The proposed MISO-J2982 project is a 35 MW solar generation project located in Warren County, Illinois. Interconnection was requested by the developer to the Midcontinent Independent System Operator (MISO) on September 14, 2022, with a proposed commercial operation date of September 30, 2023. The project is currently in the Cluster Study phase of the interconnection process. Ameren Illinois is the utility associated with the project.
The point of interconnection (POI) for the proposed project is the Line 6629 Monmouth 69 kV Switching Station. The project consists solely of 35 MW of solar photovoltaic generation. The project is listed as "active" in the MISO interconnection queue.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IL
County
Warren
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
NRIS
Point of Interconnection
Line 6629 Monmouth 69 kV Switching Station
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J2982Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.