MISO-J2908
30 MW generation in Morgan, IL · In queue since July 2022 · Proposed COD July 2023
30 MW
Capacity
1
Components
Solar
4 years
In Queue
Cluster Study
IA Phase
COD target: 2023
Total Duration
1 year
Schedule
36 months past proposed COD
Study Phase
DPP-2022 Central
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-07-30
MISO-J2908 is a proposed 30 MW solar generation project located in Morgan County, Illinois. The project is interconnected within the Midcontinent Independent System Operator (MISO) region to Ameren Illinois, and entered the MISO queue on July 27, 2022. Its proposed commercial operation date is July 30, 2023. The project's interconnection status is currently in the Cluster Study phase.
The proposed project consists of 30 MW of solar photovoltaic generation. The point of interconnection (POI) for the project is Jacksonville North. The project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
Realization history for this asset — final cost vs plan, COD slip vs original date, and construction duration vs cohort. Retrospective context for the operating risk view above. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IL
County
Morgan
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
NRIS/ERIS
Point of Interconnection
Jacksonville North
Data Source
LBNL + Live
Composite operating risk view for this asset — climate hazards across its remaining operating life, observed generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — 10-year P50 trajectory accounting for degradation, observed curtailment, and market conditions, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this asset — 10-year cashflow projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- HIGH
- POI Substation
- Jacksonville North Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J2908Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.