MISO-J2815
140 MW generation in Calhoun, MI · In queue since August 2022 · Proposed COD February 2026
140 MW
Capacity
1
Components
Solar
3y 11m
In Queue
Cluster Study
IA Phase
Signed Aug 2025
Queue → IA
3 years
IA → COD
6 months
Total Duration
3 years
Schedule
5 months past proposed COD
Study Phase
DPP-2022 East (ITC)
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-02-14
MISO-J2815 is a proposed solar generation project located in Calhoun County, Michigan, with a total capacity of 140 MW. The project, interconnected within the Midcontinent Independent System Operator (MISO) region, entered the MISO queue on August 30, 2022, and has a proposed commercial operation date of February 15, 2025. The project's interconnection status is currently in the Cluster Study phase.
The proposed project is being developed within the service territory of METC. The point of interconnection is the Argenta - Verona 138kV Line. The project has appeared in recent news coverage regarding renewable energy development in the MISO region.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MI
County
Calhoun
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
NRIS
Point of Interconnection
ARGENTA - VERONA 138.0kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Verona
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J2815Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.