Project MISO-J2801 — Project Summary

Queue ID
MISO-J2801
Capacity
130 MW
Technology
Solar
Status
active
Location
Woodruff, AR
Region
MISO
Developer
IA Status
Cluster Study

MISO-J2801

MISO-J2801BetaActiveSolarMISOLBNL + Live

130 MW generation in Woodruff, AR · In queue since September 2023 · Proposed COD September 2026

BA: MISOISO/RTO: MISONERC: SERCRC: MISO

130 MW

Capacity

1

Components

Solar

2y 10m

In Queue

Cluster Study

IA Phase

COD target: 2026

Interconnection

Total Duration

3 years

Study Phase

DPP-2022 South

Impact Study25%
Queue EntrySep 11, 2023

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-09-01

About

MISO-J2801 is a proposed solar generation project located in Woodruff County, Arkansas, within the Midcontinent Independent System Operator (MISO) region. The development project, with a total capacity of 130 MW, is being proposed by Entergy Arkansas. It consists of 130 MW of solar photovoltaic generation.

The project entered the MISO interconnection queue on September 11, 2023, and has a proposed commercial operation date of September 1, 2026. Its interconnection agreement status is currently listed as "In Progress (unknown study)". The point of interconnection is the AECC Hunter North-McCrory 161 kV substation.

Generated from interconnection queue and public data sources

Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

AR

County

Woodruff

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Utility

ENTERGY ARKANSAS

Entity

MISO

Service Type

ERIS

Point of Interconnection

AECC HUNTER NORTH - MCCRORY 161.0kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
MISO
Trading Hub
ARKANSAS.HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.

No Ask reports yet for this entity.

Ask about Project MISO-J2801
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.