MISO-J2797
150 MW hybrid in White, IL · In queue since October 2025 · Proposed COD September 2026
150 MW
Capacity
1
Components
Solar
9 months
In Queue
Cluster Study
IA Phase
COD target: 2026
Total Duration
11 months
Study Phase
DPP-2022 Central
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-15
The proposed MISO-J2797 project is a 150 MW hybrid solar and battery energy storage development project located in White County, Illinois. Interconnection is being managed through the Midcontinent Independent System Operator (MISO) queue, with an initial queue entry date of September 15, 2022. The proposed commercial operation date is September 15, 2026.
The project, which will interconnect with Ameren Illinois at the 7NORRIS 345kV point of interconnection, is currently in the Cluster Study phase of the interconnection process. The project consists of 150 MW of solar generation capacity.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IL
County
White
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
NRIS
Point of Interconnection
Norris City North
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J2797Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.