MISO-J2786
170 MW hybrid in Allegan, MI · In queue since September 2022 · Proposed COD July 2024
170 MW
Capacity
1
Components
Solar
3y 10m
In Queue
Cluster Study
IA Phase
COD target: 2024
Total Duration
1y 10m
Schedule
25 months past proposed COD
Study Phase
DPP-2022 East (ITC)
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-07-01
MISO-J2786 is a proposed hybrid solar and battery project with a total capacity of 189.25 MW. The project is located in Allegan County, Michigan, and is interconnected within the Midcontinent Independent System Operator (MISO) region. The queue entry date is September 15, 2022, with a proposed commercial operation date of July 1, 2024. The interconnection agreement (IA) status is listed as "In Progress (unknown study)". The point of interconnection (POI) is the ARGENTA - TALLMADGE 345.0kV line.
The project, developed under the utility METC, consists of 189.25 MW of solar capacity. The project is listed as active in the MISO interconnection queue. The project has appeared in recent news coverage regarding renewable energy development in the region.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MI
County
Allegan
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
NRIS
Point of Interconnection
ARGENTA - TALLMADGE 345.0kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J2786Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.