MISO-J2519
600 MW generation in Richland Parish, LA · In queue since September 2022 · Proposed COD October 2026
600 MW
Capacity
1
Components
Solar
4y 2m
In Queue
Cluster Study
IA Phase
COD target: 2026
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 1m
Schedule
1 months past proposed COD
Study Phase
DPP-2022 South
Interconnection request submitted to ISO/RTO
Active; post-GIA Not Started; Phase 2
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-10-31
About
Generated Apr 10, 2026 · Predates Oct 25, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The proposed MISO-J2519 project is a 600 MW solar generation facility located in Richland Parish, Louisiana. The project, which is being developed within the Entergy Louisiana service area, entered the MISO interconnection queue on September 13, 2022. Its proposed commercial operation date is October 31, 2026.
The interconnection agreement for the project is currently listed as "In Progress (unknown study)". The point of interconnection is the Baxter Wilson SES SWYD - Perryville 500 500 kV. The project has appeared in recent news.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- MISO queue source as of: Oct 25, 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
LA
County
Richland Parish
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY LOUISIANA
Entity
MISO
Service Type
ERIS
Point of Interconnection
Smalling
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
Solar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Louisiana in Louisiana growth signals — PPAs, construction, new projects
Summary analysis with parallel narrative sections and visualizations.
AEP Jacksonville Solar Project
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.