MISO-J2490
125 MW generation in Tuscola, MI · In queue since September 2022 · Proposed COD November 2025
125 MW
Capacity
1
Components
Solar
3y 10m
In Queue
Cluster Study
IA Phase
COD target: 2025
Total Duration
3y 2m
Schedule
8 months past proposed COD
Study Phase
DPP-2022 East (ITC)
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-11-01
MISO-J2490 is a proposed solar generation project located in Tuscola County, Michigan, with a total capacity of 125 MW. The project, interconnected with ITC, entered the MISO interconnection queue on September 14, 2022, and has a proposed commercial operation date of November 1, 2025. Its interconnection status is currently in the Cluster Study phase.
The project consists of 125 MW of solar photovoltaic generation. The point of interconnection is the Tuscola-Arrowhead 120kV Transmission Line.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MI
County
Tuscola
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC
Entity
MISO
Service Type
NRIS
Point of Interconnection
Tuscola-Arrowhead 120kV Transmission Line
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J2490Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.