MISO-J2322
200 MW generation in Evangeline Parish, LA · In queue since November 2025 · Proposed COD July 2025
200 MW
Capacity
1
Components
Solar
8 months
In Queue
Cluster Study
IA Phase
COD target: 2025
Total Duration
8 months
Schedule
12 months past proposed COD
Study Phase
DPP-2022 South
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-07-02
MISO-J2322 is a proposed 200 MW solar generation project located in Evangeline Parish, Louisiana. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of May 17, 2022, and a proposed commercial operation date of July 2, 2025. The interconnecting utility is CLECO POWER.
The interconnection agreement (IA) status for MISO-J2322 is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Pine Prairie to Coughlin 138 kV line. The project is currently listed as active in the MISO queue.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
LA
County
Evangeline Parish
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
CLECO POWER
Entity
MISO
Service Type
ERIS
Point of Interconnection
Coughlin - Pine Prairie 138.0kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- HIGH
- POI Substation
- Pine
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J2322Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.