MISO-J2314
150 MW generation in Liberty, TX · In queue since September 2021 · Proposed COD December 2023
150 MW
Capacity
1
Components
Solar
5y 1m
In Queue
IA Pending
IA Phase
COD target: 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
2y 3m
Schedule
34 months past proposed COD
Study Phase
DPP-2021 South
Interconnection request submitted to ISO/RTO
Done; post-GIA Not Started; Phase 3
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-31
MISO-J2314 is a proposed 150 MW solar generation project located in Liberty County, Texas. The development project is listed in the interconnection queue of the Midcontinent Independent System Operator (MISO), with Entergy Texas, Inc. as the associated transmission utility. The project is designed to connect to the grid at the Petry Woods substation and has requested Network Resource Interconnection Service (NRIS). No developer or project name has been publicly identified in the available queue data.
The project entered the MISO queue on September 10, 2021, and remains in active status. It is being evaluated as part of the DPP-2021 South study cycle. Its interconnection agreement is currently pending. The proposed commercial operation date listed in the queue is December 31, 2023, which has already passed without the project reaching completion.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Liberty
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY TEXAS, INC.
Entity
MISO
Service Type
NRIS
Point of Interconnection
PETRY WOODS SS
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- TEXAS.HUB
- Hub Confidence
- HIGH
- POI Substation
- Petry Woods Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J2314Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.