MISO-J2272
250 MW hybrid in Clinton, IA · In queue since July 2021 · Proposed COD September 2024
250 MW
Capacity
1
Components
Solar
5y 4m
In Queue
Cluster Study
IA Phase
COD target: 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 2m
Schedule
27 months past proposed COD
Study Phase
DPP-2021 West
Interconnection request submitted to ISO/RTO
Active; post-GIA Not Started; Phase 2
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-01
About
Generated Apr 10, 2026 · Predates Oct 25, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
MISO-J2272 is a proposed 250 MW hybrid solar and battery project located in Clinton County, Iowa. The project consists of 250 MW of solar generation. It is interconnected within the Midcontinent Independent System Operator (MISO) queue as of July 22, 2021, with a proposed commercial operation date of September 1, 2024. The project's interconnection agreement status is listed as "In Progress (unknown study)" and the point of interconnection is the 161kV East Calamus Substation, served by ITC Midwest.
The development project is listed in the MISO interconnection queue under queue ID MISO-J2272.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- MISO queue source as of: Oct 25, 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IA
County
Clinton
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC MIDWEST
Entity
MISO
Service Type
NRIS
Point of Interconnection
Calamus East
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Calamus East Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J2272Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.