MISO-J2262
625 MW generation in Jackson, AR · In queue since October 2021 · Proposed COD July 2029
625 MW
Capacity
1
Components
Solar
5 years
In Queue
IA Pending
IA Phase
Signed Dec 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
4y 2m
IA → COD
3y 7m
Total Duration
4y 2m
Study Phase
DPP-2021 South
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Not Started; Phase 3
Project under construction
Typical: 12–24 months
Proposed COD: 2029-07-20
MISO-J2262 is a proposed 625 MW solar generation project located in Jackson County, Arkansas. The development project is situated within the service territory of Entergy Arkansas and would interconnect to the grid at the Independence–ISES–Powerline Road 500 kV transmission line. No developer name has been disclosed in the available queue data. The project has requested Network Resource Interconnection Service (NRIS), which would allow its output to be used to serve network load within the regional transmission system.
The project entered the Midcontinent Independent System Operator (MISO) interconnection queue on October 11, 2021, and remains in active status. It is being evaluated as part of the DPP-2021 South study cycle. As of the latest data, its interconnection agreement (IA) status is listed as "IA Pending," with an associated IA date of December 11, 2025. The proposed commercial operation date for the project is July 20, 2029.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
AR
County
Jackson
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY ARKANSAS
Entity
MISO
Service Type
NRIS
Point of Interconnection
INDEPENDENCE-ISES - POWERLINE ROAD 500.0kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- ARKANSAS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J2262Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.