MISO-J2249
144 MW generation in Acadia Parish, LA · In queue since December 2021 · Proposed COD October 2024
144 MW
Capacity
1
Components
Solar
4y 10m
In Queue
IA Pending
IA Phase
Signed Dec 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
4 years
Total Duration
4 years
Schedule
24 months past proposed COD
Study Phase
DPP-2021 South
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Not Started; Phase 3
Project under construction
Typical: 12–24 months
Proposed COD: 2024-10-31
MISO-J2249 is a proposed 144 MW solar generation project located in Acadia Parish, Louisiana. The development project consists of a single solar component and is listed in the interconnection queue of the Midcontinent Independent System Operator (MISO), with Entergy Louisiana as the associated utility. The project is proposed to interconnect at the Bayou Cove point of interconnection and has requested Network Resource Interconnection Service (NRIS).
The project entered the MISO queue on December 21, 2021, and is currently listed with an active status. It is being evaluated in the DPP-2021 South study phase of MISO's Definitive Planning Phase process. Its interconnection agreement status is recorded as "IA Pending," with an associated IA date of December 9, 2025. The project's proposed commercial operation date was October 31, 2024, a date that precedes the listed IA date.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
LA
County
Acadia Parish
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY LOUISIANA
Entity
MISO
Service Type
NRIS
Point of Interconnection
Bayou Cove
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J2249Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.