MISO-J2238
200 MW hybrid in Maries, MO · In queue since July 2025 · Proposed COD February 2024
200 MW
Capacity
1
Components
Solar
1 year
In Queue
Cluster Study
IA Phase
COD target: 2024
Total Duration
1 year
Schedule
29 months past proposed COD
Study Phase
DPP-2021 Central
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-02-15
MISO-J2238 is a proposed 200 MW hybrid solar and battery project located in Maries County, Missouri. The development project, which consists of 200 MW of solar capacity, is in the MISO interconnection queue as of March 18, 2022, with a proposed commercial operation date of February 15, 2024. Ameren Missouri is the utility associated with the project.
The project's interconnection status is currently listed as "Cluster Study". The point of interconnection is the The Franks (Bus #300041) - Bland (Bus #344154) 345 kV Line.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MO
County
Maries
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN MISSOURI
Entity
MISO
Service Type
NRIS
Point of Interconnection
The Franks (Bus #300041) - Bland (Bus #344154) 345 kV Line
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J2238Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.