MISO-J2205
300 MW hybrid in Callaway, MO · In queue since August 2021 · Proposed COD September 2024
300 MW
Capacity
1
Components
Solar
4y 11m
In Queue
Cluster Study
IA Phase
COD target: 2024
Total Duration
3y 1m
Schedule
23 months past proposed COD
Study Phase
DPP-2021 Central
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-01
The proposed MISO-J2205 project is a 300 MW solar and battery hybrid development in Callaway County, Missouri. Interconnecting within the Midcontinent Independent System Operator (MISO) region, the project entered the queue on August 12, 2021, with a proposed commercial operation date of September 1, 2024. The project, which is being developed within the Ameren Missouri service area, consists of 300 MW of solar generation capacity.
The interconnection request is currently in the Cluster Study phase. The point of interconnection (POI) is the J1145 New 345kV POI Substation on the Ameren Overton-Montgomery 345kV Line.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MO
County
Callaway
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN MISSOURI
Entity
MISO
Service Type
NRIS
Point of Interconnection
J1145 New 345kV POI Substation (Ameren Overton-Montgomery 345kV Line)
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- HIGH
- POI Substation
- Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J2205Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.