MISO-J2069
100 MW hybrid in Montcalm, MI · In queue since November 2021 · Proposed COD June 2027
100 MW
Capacity
1
Components
Solar
4y 8m
In Queue
Cluster Study
IA Phase
Signed Dec 2025
Queue → IA
4y 1m
IA → COD
1y 6m
Total Duration
4y 1m
Study Phase
DPP-2021 East (ITC)
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2027-06-07
MISO-J2069 is a proposed 100 MW hybrid solar and battery energy storage project located in Montcalm County, Michigan. The project, interconnecting with ITC, entered the MISO interconnection queue on November 30, 2021, with a proposed commercial operation date of September 1, 2024. The project's interconnection status is currently in the Cluster Study phase.
The development project consists of 100 MW of solar generation capacity coupled with battery storage. It is listed in the MISO queue under queue ID MISO-J2069.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MI
County
Montcalm
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC
Entity
MISO
Service Type
NRIS
Point of Interconnection
EUREKA - VESTABURG 138.0kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J2069Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.