MISO-J2068
75 MW generation in Pierce, WI · In queue since July 2021 · Proposed COD November 2024
75 MW
Capacity
1
Components
Solar
5 years
In Queue
Cluster Study
IA Phase
COD target: 2024
Total Duration
3y 4m
Schedule
20 months past proposed COD
Study Phase
DPP-2021 West
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-11-30
MISO-J2068 is a proposed solar generation project located in Pierce County, Wisconsin, within the Midcontinent Independent System Operator (MISO) region. The project, with a total capacity of 75 MW, consists entirely of solar photovoltaic technology. Northern States Power Company is the utility associated with the project.
The project entered the MISO interconnection queue on July 19, 2021, and has a proposed commercial operation date of November 30, 2024. Its interconnection agreement status is currently listed as "In Progress (unknown study)". The point of interconnection is the Herbert 69 kV Substation.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
WI
County
Pierce
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
NORTHERN STATES POWER COMPANY
Entity
MISO
Service Type
NRIS
Point of Interconnection
Herbert 69 kV Substation
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J2068Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.