MISO-J2031
100 MW generation in Tama, IA · In queue since August 2021 · Proposed COD December 2026
100 MW
Capacity
1
Components
Wind
4y 11m
In Queue
Cluster Study
IA Phase
COD target: 2026
Total Duration
5y 4m
Study Phase
DPP-2021 West
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-15
MISO-J2031 is a proposed 100 MW wind generation project located in Tama County, Iowa. The project, which consists of 100 MW of wind capacity, is interconnected with ITC MIDWEST and is currently active in the Midcontinent Independent System Operator (MISO) interconnection queue. The project entered the queue on August 13, 2021, with a proposed commercial operation date of March 13, 2024. Its interconnection agreement status is listed as "In Progress (unknown study)".
The proposed project is located at the point of interconnection (POI) named Toledo. The developer is not specified in the queue data. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IA
County
Tama
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC MIDWEST
Entity
MISO
Service Type
NRIS
Point of Interconnection
Toledo
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Toledo Transmission Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J2031Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.