MISO-J1916
100 MW generation in Branch, MI · In queue since October 2023 · Proposed COD March 2026
100 MW
Capacity
1
Components
Solar
2y 9m
In Queue
Cluster Study
IA Phase
Signed Jul 2025
Queue → IA
1y 9m
IA → COD
8 months
Total Duration
1y 9m
Schedule
4 months past proposed COD
Study Phase
DPP-2021 East (ITC)
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-03-06
MISO-J1916 is a proposed 100 MW solar generation project located in Branch County, Michigan. The project, interconnected within the Midcontinent Independent System Operator (MISO) region, entered the MISO queue on October 19, 2023, with a proposed commercial operation date of November 1, 2023. The project's interconnection status is currently in the Cluster Study phase.
The proposed project is to be connected to the Newton 138 kV substation. The queue entry lists the utility as METC and the entity as MISO.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MI
County
Branch
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
NRIS
Point of Interconnection
NEWTON
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Newton Eighth Street Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J1916Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.