MISO-J1902
200 MW storage in Wayne, MI · In queue since August 2021 · Proposed COD September 2024
200 MW
Capacity
1
Components
Battery
4y 11m
In Queue
Cluster Study
IA Phase
COD target: 2024
Total Duration
3y 1m
Schedule
22 months past proposed COD
Study Phase
DPP-2021 East (ITC)
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-30
MISO-J1902 is a proposed 200 MW battery storage project located in Wayne County, Michigan. The project, which consists entirely of battery storage, is in the Midcontinent Independent System Operator (MISO) interconnection queue. The queue entry date is August 13, 2021, with a proposed commercial operation date of September 30, 2024. The project's interconnection status is currently in the Cluster Study phase.
The project is interconnected with ITC and is listed in the MISO queue. No developer is specified in the queue data. The point of interconnection (POI) is the Ironton 120 kV substation. The project has appeared in recent news coverage regarding energy storage development in the region.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MI
County
Wayne
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC
Entity
MISO
Service Type
NRIS
Point of Interconnection
IRONTON
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Ironton Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J1902Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.