MISO-J1870
200 MW generation in Tangipahoa Parish, LA · In queue since August 2021 · Proposed COD September 2024
200 MW
Capacity
1
Components
Solar
5y 2m
In Queue
IA Pending
IA Phase
Signed Oct 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
4y 2m
Total Duration
4y 2m
Schedule
26 months past proposed COD
Study Phase
DPP-2021 South
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Not Started; Phase 3
Project under construction
Typical: 12–24 months
Proposed COD: 2024-09-15
MISO-J1870 is a proposed 200 MW solar generation project located in Tangipahoa Parish, Louisiana. The development project is listed as active in the interconnection queue of the Midcontinent Independent System Operator (MISO), within the service territory of Entergy Louisiana. It would interconnect at the Independence Substation 230 kV point of interconnection. No developer or project name is identified in the available queue data.
The project entered the MISO queue on August 16, 2021, and is being studied in the DPP-2021 South cycle of MISO's Definitive Planning Phase. It has requested Network Resource Interconnection Service (NRIS). Its proposed commercial operation date was September 15, 2024. The project's interconnection agreement status is listed as "IA Pending," with an associated IA date of October 30, 2025.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
LA
County
Tangipahoa Parish
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY LOUISIANA
Entity
MISO
Service Type
NRIS
Point of Interconnection
Independence Substation 230kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- ALTW.INDEPWIND
- POI Substation
- Independence Wind Farm
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J1870Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.