MISO-J1836
300 MW generation in Callaway, MO · In queue since June 2020 · Proposed COD August 2025
300 MW
Capacity
1
Components
Solar
6y 4m
In Queue
IA Pending
IA Phase
COD target: 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 2m
Schedule
15 months past proposed COD
Study Phase
DPP-2020 Central
Interconnection request submitted to ISO/RTO
Done; post-GIA Not Started; GIA
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-08-01
MISO-J1836 is a proposed 300 MW solar generation project located in Callaway County, Missouri. The development project is listed in the interconnection queue of the Midcontinent Independent System Operator (MISO), with Ameren Missouri as the associated transmission utility. No developer is identified in the available data. The project consists of a single solar component with a capacity of 300 MW. It would interconnect at the Montgomery–Callaway 7 point of interconnection.
The project entered the MISO queue on June 23, 2020, and remains in active status. It is being studied in the DPP-2020 Central study cycle and has requested Network Resource Interconnection Service (NRIS). The proposed commercial operation date is August 1, 2025. As of the latest data, the project's interconnection agreement is pending.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MO
County
Callaway
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN MISSOURI
Entity
MISO
Service Type
NRIS
Point of Interconnection
Montgomery- Callaway- 7
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J1836Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.