MISO-J1834
126 MW generation in Orange, TX · In queue since December 2021 · Proposed COD April 2025
126 MW
Capacity
1
Components
Gas
4y 10m
In Queue
IA Pending
IA Phase
Signed Feb 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 2m
IA → COD
1y 2m
Total Duration
2y 2m
Schedule
18 months past proposed COD
Study Phase
DPP-2020 South
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Not Started; GIA
Project under construction
Typical: 24–48 months
Proposed COD: 2025-04-25
MISO-J1834 is a proposed 126 MW natural gas-fired generation project located in Orange County, Texas. The development project is in the interconnection queue of the Midcontinent Independent System Operator (MISO), with Entergy Texas, Inc. as the associated transmission utility. The project proposes to interconnect at the Sabine 138/230 kV Substation and has requested Network Resource Interconnection Service (NRIS). No developer or project name has been publicly identified in the queue data.
The project entered the MISO queue on December 16, 2021, and remains in active status. It is being evaluated as part of the DPP-2020 South study phase. Its interconnection agreement (IA) is listed as pending, with an associated IA date of February 21, 2024. The proposed commercial operation date is April 25, 2025.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Orange
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY TEXAS, INC.
Entity
MISO
Service Type
NRIS
Point of Interconnection
Sabine 138/230 kV Substation
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- TEXAS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J1834Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.