MISO-J1816
135 MW generation in Cross, AR · In queue since March 2022 · Proposed COD October 2025
135 MW
Capacity
1
Components
Solar
4y 7m
In Queue
IA Pending
IA Phase
Signed May 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 2m
IA → COD
2y 5m
Total Duration
1y 2m
Schedule
12 months past proposed COD
Study Phase
DPP-2020 South
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Not Started; GIA
Project under construction
Typical: 12–24 months
Proposed COD: 2025-10-30
MISO-J1816 is a proposed 135 MW solar generation project in Cross County, Arkansas, within the Midcontinent Independent System Operator (MISO) region. The development project consists entirely of solar photovoltaic capacity and would interconnect to the transmission system at the Fisher – Cherry Valley 161.0 kV point of interconnection, in the service territory of Entergy Arkansas. No developer or project name has been publicly identified in the queue data.
The project entered the MISO interconnection queue on March 17, 2022, and remains in active status. It is being studied as part of the DPP-2020 South study cycle and has requested Network Resource Interconnection Service (NRIS). Its interconnection agreement (IA) status is listed as pending, with an associated IA date of May 11, 2023. The proposed commercial operation date for the project is October 30, 2025.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
AR
County
Cross
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY ARKANSAS
Entity
MISO
Service Type
NRIS
Point of Interconnection
FISHER - CHERRY VALLEY 161.0kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- ARKANSAS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J1816Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.