MISO-J1798
25 MW generation in Wayne, MI · In queue since June 2020 · Proposed COD June 2021
25 MW
Capacity
1
Components
Gas
6y 4m
In Queue
IA Executed
IA Phase
COD target: 2021
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
1 year
Schedule
66 months past proposed COD
Study Phase
DPP-2020 East (ITC)
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Not Started; GIA
Project under construction
Typical: 24–48 months
Proposed COD: 2021-06-01
MISO-J1798 is a proposed 25 MW natural gas-fired generation project located in Wayne County, Michigan. The development project is listed in the interconnection queue of the Midcontinent Independent System Operator (MISO), with ITC serving as the interconnecting transmission utility. The project would connect to the grid at the Waterman 120kV point of interconnection and has requested Energy Resource Interconnection Service (ERIS). No developer or project name is identified in the queue data.
The project entered the MISO interconnection queue on June 24, 2020, and was studied as part of the DPP-2020 East (ITC) study cycle. It holds an active status in the queue, and an interconnection agreement (IA) has been executed. The proposed commercial operation date was June 1, 2021.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MI
County
Wayne
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC
Entity
MISO
Service Type
ERIS
Point of Interconnection
Waterman 120kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- DECO.DLRYP11
- POI Substation
- Waterman Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J1798Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.