MISO-J1779
200 MW hybrid in Dane, WI · In queue since September 2021 · Proposed COD October 2024
200 MW
Capacity
1
Components
Solar
5y 1m
In Queue
IA Executed
IA Phase
Signed Oct 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 1m
IA → COD
<1 month
Total Duration
3y 1m
Schedule
24 months past proposed COD
Study Phase
DPP-2020 East (ATC)
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Not Started; GIA
Project under construction
Typical: 18–30 months
Proposed COD: 2024-10-31
MISO-J1779 is a proposed solar-plus-battery hybrid development project located in Dane County, Wisconsin. The project has a total capacity of 200 MW, all of which is attributed to its solar component in the interconnection data. The battery storage component is listed as part of the project's technology, but no separate capacity is specified for it. The project is proposed to connect at the Rockdale point of interconnection, within the transmission system of the American Transmission Company (ATC). It has requested Network Resource Interconnection Service (NRIS).
The project entered the Midcontinent Independent System Operator (MISO) interconnection queue on September 1, 2021, and currently holds active status. It was studied as part of the DPP-2020 East (ATC) study phase. An interconnection agreement was executed on October 9, 2024. The project's proposed commercial operation date was October 31, 2024.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
WI
County
Dane
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMERICAN TRANSMISSION COMPANY
Entity
MISO
Service Type
NRIS
Point of Interconnection
Rockdale
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- ALTE.1ROCKGEN
- POI Substation
- Rockdale Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.