MISO-J1760
205 MW generation in Liberty, TX · In queue since June 2020 · Proposed COD October 2023
205 MW
Capacity
1
Components
Solar
6y 4m
In Queue
IA Executed
IA Phase
Signed Jan 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 7m
IA → COD
9 months
Total Duration
2y 7m
Schedule
37 months past proposed COD
Study Phase
DPP-2020 South
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Not Started; GIA
Project under construction
Typical: 12–24 months
Proposed COD: 2023-10-01
MISO-J1760 is a proposed 205 MW solar generation project located in Liberty County, Texas. The development project is situated within the Midcontinent Independent System Operator (MISO) footprint, with Entergy Texas, Inc. serving as the interconnecting utility. The project would connect to the grid at the Timberland 230kV point of interconnection. No developer or project name has been publicly identified in the available queue data.
The project entered the MISO interconnection queue on June 15, 2020, and was evaluated as part of the DPP-2020 South study cycle. It has requested Network Resource Interconnection Service (NRIS). An interconnection agreement was executed on January 18, 2023, and the project remains in active status in the queue. The proposed commercial operation date was listed as October 1, 2023.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Liberty
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY TEXAS, INC.
Entity
MISO
Service Type
NRIS
Point of Interconnection
Timberland 230kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- TEXAS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J1760Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.