MISO-J1748
100 MW generation in Desoto, MS · In queue since July 2020 · Proposed COD August 2023
100 MW
Capacity
1
Components
Solar
6y 3m
In Queue
IA Executed
IA Phase
Signed Nov 2022
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 4m
IA → COD
9 months
Total Duration
2y 4m
Schedule
39 months past proposed COD
Study Phase
DPP-2020 South
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Not Started; GIA
Project under construction
Typical: 12–24 months
Proposed COD: 2023-08-15
MISO-J1748 is a proposed 100 MW solar generation project located in DeSoto County, Mississippi. The development project is listed in the interconnection queue of the Midcontinent Independent System Operator (MISO), with Entergy Mississippi, LLC serving as the interconnecting utility. No developer or project name is identified in the available queue data. The project is designed to connect to the grid at the Twinkletown 230 kV point of interconnection and has requested Network Resource Interconnection Service (NRIS).
The project entered the MISO queue on July 17, 2020, and was evaluated as part of the DPP-2020 South study cycle. Its interconnection agreement (IA) was executed on November 29, 2022. The project had a proposed commercial operation date of August 15, 2023, and its queue status remains active.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MS
County
Desoto
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY MISSISSIPPI, LLC.
Entity
MISO
Service Type
NRIS
Point of Interconnection
Twinkletown 230 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J1748Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.