Project MISO-J1664 — Project Summary

Queue ID
MISO-J1664
Capacity
200 MW
Technology
Solar
Status
active
Location
St. Clair, MI
Region
MISO
Developer
—
IA Status
IA Executed

MISO-J1664

MISO-J1664BetaActiveSolarMISOLBNL + Live

200 MW generation in St. Clair, MI · In queue since June 2020 · Proposed COD September 2023

BA: MISOISO/RTO: MISONERC: RFCRC: MISO

200 MW

Capacity

1

Components

Solar

6y 4m

In Queue

IA Executed

IA Phase

Signed Dec 2024

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

4 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

4y 6m

Total Duration

4y 6m

Schedule

38 months past proposed COD

Study Phase

DPP-2020 East (ITC)

Construction75%
Queue EntryJun 24, 2020

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection AgreementDec 26, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Done; post-GIA Not Started; GIA

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2023-09-01

About

MISO-J1664 is a proposed 200 MW solar generation project located in St. Clair County, Michigan. The development project consists of a single solar component with a capacity of 200 MW and would connect to the transmission system at the Carrigan 120kV Substation, within the service territory of the transmission utility ITC. No developer or project name has been publicly identified in the interconnection queue data.

The project entered the Midcontinent Independent System Operator (MISO) interconnection queue on June 24, 2020, and remains in active status. It was studied as part of the DPP-2020 East (ITC) study cycle and has requested Network Resource Interconnection Service (NRIS). The project's original proposed commercial operation date was September 1, 2023, a date that has since passed without the project being recorded as operational. An interconnection agreement (IA) was executed on December 26, 2024, marking a significant milestone in the project's progression through the MISO interconnection process.

Generated from interconnection queue and public data sources

Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

MI

County

St. Clair

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

—

Utility

ITC

Entity

MISO

Service Type

NRIS

Point of Interconnection

Carrigan 120kV Substation

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
MISO
Trading Hub
MICHIGAN.HUB
Hub Confidence
HIGH
POI Substation
Carrigan Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.

No Ask reports yet for this entity.

Ask about Project MISO-J1664
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.