MISO-J1663
200 MW generation in Ottawa, MI · In queue since December 2021 · Proposed COD September 2023
200 MW
Capacity
1
Components
Solar
4y 10m
In Queue
Construction
IA Phase
Signed Mar 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 3m
IA → COD
6 months
Total Duration
1y 3m
Schedule
38 months past proposed COD
Study Phase
DPP-2020 East (ITC)
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Under Construction; GIA
Project under construction
Typical: 12–24 months
Proposed COD: 2023-09-15
MISO-J1663 is a proposed 200 MW solar generation project located in Ottawa County, Michigan. The development project is listed in the interconnection queue of the Midcontinent Independent System Operator (MISO), with Michigan Electric Transmission Company (METC) identified as the associated transmission utility. The project would connect to the grid at the Argenta–Tallmadge 345.0 kV point of interconnection and has requested Network Resource Interconnection Service (NRIS). No developer is identified in the available data.
The project entered the MISO queue on December 3, 2021, and was studied as part of the DPP-2020 East (ITC) study phase. Its queue status is active. An interconnection agreement was executed on March 7, 2023, and the agreement status is listed as "Construction." The project's proposed commercial operation date was September 15, 2023.
Generated from interconnection queue and public data sources
Realization risk through commissioning — schedule slippage, construction cost overrun, and COD probability vs the stated window. The diligence view that determines whether the project comes online when promised. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MI
County
Ottawa
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
NRIS
Point of Interconnection
ARGENTA - TALLMADGE 345.0kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with curtailment risk decomposed by congestion zone and ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, first-year DSCR, and construction cost overrun exposure — what determines whether the deal clears its covenants once online. Projected across price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J1663Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.