180 MW generation in Hillsdale, MI · In queue since May 2025 · Proposed COD September 2023
180 MW
Capacity
1
Components
Solar
1y 5m
In Queue
IA Executed
IA Phase
COD target: 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
1y 5m
Schedule
38 months past proposed COD
Study Phase
DPP-2020 East (ITC)
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Not Started; GIA
Project under construction
Typical: 12–24 months
Proposed COD: 2023-09-01
MISO-J1658 is a proposed 180 MW solar generation project located in Hillsdale County, Michigan. The development project is listed in the interconnection queue of the Midcontinent Independent System Operator (MISO), with Michigan Electric Transmission Company (METC) as the associated transmission utility. The project consists of a single solar component totaling 180 MW, and the developer is not identified in the available queue data.
The project is currently listed as active in the MISO queue. Its recorded queue entry date is May 19, 2025, and its proposed commercial operation date is September 1, 2023. It was evaluated in the DPP-2020 East (ITC) study phase and has requested Network Resource Interconnection Service (NRIS). The proposed point of interconnection is the Coldwater–Moore Road 138.0 kV line. According to queue records, an interconnection agreement has been executed for the project.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MI
County
Hillsdale
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
NRIS
Point of Interconnection
COLDWATER - MOORE ROAD 138.0kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J1658Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.