150 MW generation in Tazewell, IL · In queue since December 2021 · Proposed COD September 2023
150 MW
Capacity
1
Components
Solar
4y 10m
In Queue
IA Pending
IA Phase
Signed May 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 5m
Total Duration
3y 5m
Schedule
38 months past proposed COD
Study Phase
DPP-2020 Central
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Not Started; GIA
Project under construction
Typical: 12–24 months
Proposed COD: 2023-09-15
MISO-J1653 is a proposed 150 MW solar generation project in Tazewell County, Illinois. The development project is in the interconnection queue of the Midcontinent Independent System Operator (MISO), within the service territory of Ameren Illinois. It would connect to the grid at the San Jose Rail 138 kV point of interconnection and has requested Network Resource Interconnection Service (NRIS). The project consists of a single solar component, and no developer is identified in the available data.
The project entered the MISO queue on December 3, 2021, and is being evaluated in the DPP-2020 Central study phase. Its status is active. The interconnection agreement is pending, with an associated IA date of May 16, 2025. The proposed commercial operation date of September 15, 2023 has already passed, so the project's timeline has evidently moved beyond its original target.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IL
County
Tazewell
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
NRIS
Point of Interconnection
San Jose Rail 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J1653Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.