Project MISO-J1620 — Project Summary

Queue ID
MISO-J1620
Capacity
125 MW
Technology
Solar
Status
active
Location
Pipestone, MN
Region
MISO
Developer
—
IA Status
IA Pending

MISO-J1620

MISO-J1620BetaActiveSolarMISOLBNL + Live

125 MW generation in Pipestone, MN · In queue since April 2024 · Proposed COD September 2023

BA: MISOISO/RTO: MISONERC: MRORC: MISO

125 MW

Capacity

1

Components

Solar

2y 6m

In Queue

IA Pending

IA Phase

Signed Jul 2024

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

4 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

3 months

Total Duration

3 months

Schedule

38 months past proposed COD

Study Phase

DPP-2020 West

Construction38%
Queue EntryApr 17, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection AgreementJul 25, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Done; post-GIA Not Started; GIA

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2023-09-01

About

MISO-J1620 is a proposed 125 MW solar generation project located in Pipestone County, Minnesota. The development project is listed in the interconnection queue of the Midcontinent Independent System Operator (MISO) and would connect to the transmission system at the Split Rock – Pipestone 115.0 kV point of interconnection, within the service territory of Northern States Power Company. The project consists of a single solar component rated at 125 MW and has requested Network Resource Interconnection Service (NRIS).

The project entered the MISO queue on April 17, 2024, and is currently listed as active. It is being evaluated as part of the DPP-2020 West study phase. The queue lists a proposed commercial operation date of September 1, 2023, which precedes the recorded queue entry date. The project's interconnection agreement (IA) status is listed as "IA Pending," with an associated IA date of July 25, 2024.

Generated from interconnection queue and public data sources

Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

MN

County

Pipestone

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

—

Utility

NORTHERN STATES POWER COMPANY

Entity

MISO

Service Type

NRIS

Point of Interconnection

Split Rock - Pipestone 115.0kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
MISO
Trading Hub
MINN.HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.