MISO-J1610
100 MW generation in Sangamon, IL · In queue since June 2020 · Proposed COD August 2023
100 MW
Capacity
1
Components
Solar
6y 4m
In Queue
IA Pending
IA Phase
Signed Jun 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
5 years
Total Duration
5 years
Schedule
38 months past proposed COD
Study Phase
DPP-2020 Central
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Not Started; GIA
Project under construction
Typical: 12–24 months
Proposed COD: 2023-08-31
MISO-J1610 is a proposed 100 MW solar generation project located in Sangamon County, Illinois. The development project is listed in the interconnection queue of the Midcontinent Independent System Operator (MISO), with City Water, Light & Power serving as the associated utility. The project would connect to the grid at the Auburn North to Chatham Main 138 kV transmission line and has requested Network Resource Interconnection Service (NRIS).
The project entered the MISO queue on June 16, 2020, and is being evaluated in the DPP-2020 Central study phase. Its queue status is active. The proposed commercial operation date was August 31, 2023, a date that has since passed. The interconnection agreement (IA) status is listed as "IA Pending," with an associated IA date of June 12, 2025.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IL
County
Sangamon
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
CITY WATER LIGHT & POWER
Entity
MISO
Service Type
NRIS
Point of Interconnection
Auburn North to Chatham Main 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- HIGH
- POI Substation
- Auburn
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J1610Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.